Breaking News

December 13, 2012

T-15 is open

Knoxville — The Marion County Secondary Roads Department just announced that T-15 over the Red Rock Dam is now open. 

 

The Red Rock Dam received a new bulkhead for the tainter (large flood) gates.  The bulkhead arrived at the lake, and the road closure was necessary for its installation.

The bulkhead is essentially a moveable door that can be used to block water from flowing through a tainter gate when maintenance is needed.  The bulkhead will rest on a platform along the south side of the dam (lake side) when not in use.  If repairs or other maintenance work needs to be done on a tainter gate, the bulkhead will travel along a rail system and be positioned in front of it - a crane system and transport rail will also be added to the dam’s structure for this purpose.

The bulkhead measures 66 feet wide, 25 feet tall, 3.5 feet thick, and weighs 75 tons.   It arrived in two separate pieces on oversized loads from the subcontractor’s manufacturing facility in Lackawanna, New York.  Once on-site (at the South Overlook Recreation Area), contractors bolted and welded the two pieces together.  It was then transported in one piece onto the dam for installation.

Once the project is completed, the new bulkhead will allow the Corps to perform maintenance on the tainter gates without a need to lower the lake.

1
Text Only
Breaking News
Features
AP Video
Trump: DC Hotel Will Be Among World's Best Republicans Hold a Hearing on IRS Lost Emails Ex-NYC Mayor: US Should Allow Flights to Israel David Perdue Wins Georgia GOP Senate Runoff 98-Year-Old Woman Left in Parked Truck Home-sharing Programs Help Seniors Last Mass Lynching in U.S. Remains Unsolved Disabled Veterans Memorial Nearing Completion Raw: MD Church Built in 1773 Ravaged by Fire Flight to Tel Aviv From US Diverted to Paris AP Review: Amazon Fire Adds Spark to Smartphones Judge Ponders Overturning Colo. Gay Marriage Ban NYPD Chief Calls for 'use of Force' Retraining VA Nominee McDonald Goes Before Congress Airlines Halt Travel to Israel Amid Violence US Official: Most Migrant Children to Be Removed Police Probing Brooklyn Bridge Flag Switch CDC Head Concerned About a Post-antibiotic Era Raw: First Lady Says `Drink Up' More Water Raw: Massive Fire Burns in North Dakota Town
Facebook
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Poll

Upon completion and reopening of Third Street, should the City of Knoxville wait to start the next stage of the Streetscape and Infrastructure project until 2015?

Yes
No
     View Results