Marion County — The Marion County Secondary Roads has just released a new list of current road closures due to construction. They are:

Hwy G46/T-15 Exchange – this work should be completed tomorrow, 9/6

The week of September 16th, crews will be working on crack sealing on Hwy T-17 south of Pella.  This will take approximately 2-3 days to complete.  One-way traffic and delays should be expected.  

T-14 – Crack Sealing is complete.  This crew has moved to Hwy G-76, they will work there through the end of the week and then move to Hwy G40.  This work should be done by Wednesday, September 11th.  

240th Pl Bridge Closure (over the Skunk River) – Contractors have given us Wednesday, September 11th as the day the bridge will close.  The project will take 3-4 weeks to  complete.