Video: Streetscape project hopefully done in two weeks

Knoxville — If all goes well and the weather cooperates, the concrete portion of the downtown streescape project currently under construction should be completed in two weeks. 

Inspector Richard Breese with Knoxville Public Works said he doubts that the project will be done in time for Living Windows on Nov. 21. He knows the sidewalks will not be done.

One lane of Robinson was poured today. Breese said the through streets have to be poured first. Robinson has the crown of the intersection and its installation is tied to proper drainage. 

Tomorrow (Friday, Nov. 22) the main line for the west lane of Second Street is expected to be poured, followed on Saturday by the east lane. Breese is hopeful that the south lane of Robinson can also be poured on Saturday. If not, it will be poured on Sunday. Contractors are expected be working throughout the weekend. 

After all of the road lanes reach maturity, Breese said the project will then shift to parking installation. TK Concrete and Hawkeye will be working together to install the parking space concrete. 

When the streets and parking are ready, the focus will then shift to the sidewalk. Construction of the sidewalks will be stage to ensure continued access to businesses along Second Street. The corners will then be staggered. 

While this project is referred to as "streetscape," which implies to the beautification aspect of the project, the majority of the cost and reason behind it was to update the decades-old infrastructure below. Breese said all of the underground work is complete with the exception of some electrical conduit that will be placed under the sidewalk on the east side of Second. 

Though the project has at least two more weeks of work, the original anticipated completion date for this stage of the project was Nov. 11. City Manager Harold Stewart said he does not believe any penalties will be assessed the contractor before the contact deadline for the entire project, in the spring of 2015. 

Stewart said staff has been pushing the contractors to finish this portion of the project before winter. 

 

1
Text Only
News
  • new street sign.jpg New sign installed

    A Knoxville crew installed the first of the new downtown street signs Tuesday afternoon. 

    July 22, 2014 1 Photo

  • Work on Robinson Monday morning

    Knoxville Public Works Supervisor Dennis Webb says that traffic may be congested on West Robinson this morning, between Casey's and Kent Street, for some manhole repairs. Be prepared for backed up traffic and single lanes this morning while the project is going on.

    July 21, 2014

  • Addie.jpg Team Addie benefit Aug 2

    Addie Brenden, age 3, has been diagnosed with Stage 4 Neuroblastoma. A benefit for her family is scheduled for Saturday, Aug. 2, at 10 a.m., at the North End Lounge in Pleasantville. 

    July 21, 2014 1 Photo

  • Patrick Edouard Supreme Court overturns Court of Appeals decision

    The Supreme Court of Iowa issued a ruling today which affirms a District Court ruling that sent a former Pella pastor to prison. 

    July 18, 2014 1 Photo

  • Nearwood Winery sign.jpg Nearwood Winery earns a bronze

    Nearwood Winery received a Bronze medal in the Eighth Annual Mid-American Wine Competition held at the Des Moines Area Community College campus in Ankeny.

    July 17, 2014 1 Photo

  • Knoxville Dental Center.jpg Knoxville Dental Center gets a new look

    A crew was in Knoxville Thursday, July 17, to install a new sign above the doors of the Knoxville Dental Center. 

    July 17, 2014 1 Photo

  • Dan Losada.jpg Three charged with forgery

    Three suspects were arrested in Knoxville last night for allegedly passing counterfeit bills. 

    July 16, 2014 1 Photo

  • JJ Dinner-Loebsack.jpg Loebsck rep to hold office hours

    Congressman Dave Loebsack's district representative will be at the Marion County Courthouse in Knoxville on Thursday, July 17, from 2-3 p.m. 

    July 15, 2014 1 Photo

  • CM office 2.jpg New office making progress

    Progress continues on the new City Manager's office inside Knoxville City Hall. 

    July 15, 2014 2 Photos

  • bricks July 15.jpg Brick crew will be here "until the work is done"

    The bricks for the downtown streetscape and infrastructure project remained a concern during Tuesday morning's streetscape meeting. Following a walk-through, during which every aspect of the masonry done thus far was reviewed and critiqued, the City of Knoxville was promised that workers will continue working on the project until the work is done. 

    July 15, 2014 1 Photo

Features
AP Video
Ex-NYC Mayor: US Should Allow Flights to Israel David Perdue Wins Georgia GOP Senate Runoff 98-Year-Old Woman Left in Parked Truck Home-sharing Programs Help Seniors Last Mass Lynching in U.S. Remains Unsolved Disabled Veterans Memorial Nearing Completion Raw: MD Church Built in 1773 Ravaged by Fire Flight to Tel Aviv From US Diverted to Paris AP Review: Amazon Fire Adds Spark to Smartphones Judge Ponders Overturning Colo. Gay Marriage Ban NYPD Chief Calls for 'use of Force' Retraining VA Nominee McDonald Goes Before Congress Airlines Halt Travel to Israel Amid Violence US Official: Most Migrant Children to Be Removed Police Probing Brooklyn Bridge Flag Switch CDC Head Concerned About a Post-antibiotic Era Raw: First Lady Says `Drink Up' More Water Raw: Massive Fire Burns in North Dakota Town Raw: Truck, Train Crash Leads to Fireball Courts Conflicted Over Healthcare Law
Facebook
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Poll

Upon completion and reopening of Third Street, should the City of Knoxville wait to start the next stage of the Streetscape and Infrastructure project until 2015?

Yes
No
     View Results